Project Jupiter air permit hearing pushed back without new date

State regulators and developers requested a delay to finish technical reviews, leaving the public hearing schedule undecided.

By Salma Farouk ·

Illustration for: Project Jupiter air permit hearing pushed back without new date
Illustration generated for this article, not a news photograph.

The New Mexico Environment Department and the developer behind the Project Jupiter data center asked a hearing officer to postpone a public meeting originally set for Dec. 7, citing the volume of technical evidence that still requires review.

A joint motion filed on Tuesday by the state agency and Yucca Growth Infrastructure asked hearing officer James Browning to vacate the scheduled hearing. The parties stated they needed additional time to complete a technical review of revisions to the project proposal that were submitted in October. They also required more time to publish the public notices mandated for a hearing.

During a hearing held on Thursday, Browning agreed to cancel the opening of the hearing but did not assign a new date. He ordered regular scheduling conferences to be held instead. In an order issued on Friday, Browning indicated that the hearing would be rescheduled only after the department’s Air Quality Bureau makes a recommendation.

Yucca Growth Infrastructure is the entity responsible for the on-site power generation facility for a large-scale data center under construction in Santa Teresa. The campus is being built for Oracle Corp. and OpenAI. Once completed, the site will feature four data center structures designed to support the computer capacity needed for training AI software. The project’s microgrid will use natural gas-powered fuel cell technology to generate electricity.

The delay creates an open question regarding the timeline for the state’s final decision on the permit application. The state and the developer have waived the previous decision deadline of Nov. 23. No new deadline has been established for the permit decision or the public hearing.

New Energy Economy, a clean energy advocacy organization, used the postponement to renew its request to dismiss the application in its current form. The group has argued that recent revisions to the power plan were not ready for a fair hearing. These revisions include changes to how natural gas will be piped to the site and updates to the engineering and emissions details of the fuel cell array.

An attorney for New Energy Economy told Browning on Thursday that the developers’ request for a postponement acknowledged that the application was not ready for review. The organization’s executive director, Nanasi, said in a comment to the Albuquerque Journal that the Environment Department needs time to navigate the project's uncertainties. Nanasi noted that the Bloom Energy fuel cell array envisioned for the project lacks associated engineering studies, air modeling, or other technical bases that professionals can rely on.

Browning declined to dismiss the application, stating he did not possess the technical evidence or the authority to issue such an order. He also denied a motion from the Environment Department that sought specific disclosure requirements for expert witnesses. The officer expressed doubt on Thursday that the requested order was necessary.

A legal question remains regarding the state's ability to extend the decision deadline a second time. The Environment Department previously maintained that the law permits only one extension. Browning said during the hearing that determining the legality of a second extension was not a matter for him to decide.

Construction on the data center site in Santa Teresa continues. Thousands of workers report in shifts at the location, where work began in September 2025. Yucca Growth Infrastructure did not respond to a query regarding the delay.

More News · Report a business · Got a Story?

Get Dallas County Herald in your inboxLocal news for Dallas County, Texas. Free, a few times a week, unsubscribe any time.

Get Dallas County Herald in your inboxLocal news for Dallas County, Texas. Free, a few times a week, unsubscribe any time.